Gas-plant update moves Tengiz field toward
2004 producing
target
Oil&Gas Journal Volume 98, Issue 24 (Jun 12,
2000)
by: Dave Connell
Since acquiring Tengiz oil field in West
Kazakhstan in
1993, the TengizChevroil (TCO) partnership has undertaken several
capital
investment programs and expansions that have resulted in a steady rise
in crude oil production to 9.6 million tonnes per year (tpy; 220,000
boed)
in 1999 from 1.5 million tpy in 1993.
One such project, Program 12, is one of the
current projects
required to realize sustained production at 12 million tpy. The project
will leave the Tengiz facility set for the next phases of expansion
that
will cost almost $3 billion over the next 4 years with production
expected
to reach 370,000 boed in 2004.
This article describes the LPG upgrade of $150
million
Program 12.
Tengiz oil field
Click
to enlarge
The Republic of Kazakhstan (Fig. 1)
encompasses 2.7 million
sq km; about four times the size of Texas or roughly equivalent to
Western
Europe. It is land locked at the heart of Central Asia. The land
is dominated by the vast flat grasslands of the Steppe, bordering in
the
west the Caspian Sea. The climate is arid with cold winters and hot
summers.
Click
to enlarge
Tengiz lies on the northeast Caspian shore at
the western
edge of the steppes and is subject therefore to temperature extremes,
44°
C. (111° F.) summer to -40° C. (-40° F.) Winter (Fig. 2)
The Tengiz oil field produced first oil in 1991.
The
production facility, originally implemented by the former Soviet Union
(FSU), is a world-scale capital investment.
The TCO partnership is a joint venture of
Chevron Overseas
Co., (KazakhOil) National Oil & Gas Co., Mobil Oil Kazakhstan
Ventures
Inc., and LUKarco Services BV. Oil production under TCO has grown
steadily
to 220,000 b/d from 24,000 b/d. Tengiz crude is a light high-quality
product,
with an 0.787 sp gr (48.2 API) and sulfur 0.49 wt % with light
mercaptans
5 ppm.
The Tengiz oil field, discovered in 1979, is the
largest
discovered in the last 25 years. It has 3 billion tonnes (24 billion
bbl)
of oil in place with 6-9 billion bbl of estimated recoverable oil.
The reservoir also has significant associated gas
reserves,
1,800 billion cu m (64 tcf). The reservoir is deep (target depth 4,500
m) and sour at 12.5 mol % H2S, with a relatively high temperature and
pressure
(flowing temperature 80° C., flowing pressure around 110 bar, shut-in
pressure
550 bar).
Development of the remote Tengiz field
required a major
effort to establish infrastructure. While the majority of the
infrastructure
was designed and implemented by the Russian Technical Design
Institutes,
the process plant was built by a consortium of Western contractors
(Lurgi/Litwin/Lav-
alin). Each building block or unit is called a "Complex Technology
Line"
(or "KTL," an acronym for its Russian language name). Each KTL consists
of the following:
Two trains of gas-oil separation, including
oil-water
separation and stabilization and sour-gas compression
Two trains of amine-based acid-gas removal
Two trains of Claus sulfur plant and tail-gas
treating
One common gas-processing plant
One common on-plot utility block
One common control room
It is the combination of acid-gas removal,
sulfur recovery,
high GOR, and rich associated gas that makes each KTL a substantial
facility.
Since 1993, when TCO was formed, a series of projects have been
executed
to improve and expand the infrastructure and production facilities. As
is common in oil and gas production facility design, significant
flexibility
was built in to allow for uncertainty in reservoir performance and
reservoir
composition.
Based on production experience from KTL-1 and
KTL-2 and
knowledge of the produced fluids, the first target for cost-effective
capacity
was debottlenecking. The projects executed in this period focused on
increasing
crude capacity and, consequently, production has outpaced the
gas-processing
capacity.
The next opportunity after debottlenecking was
again to
build on the existing asset and infrastructure, primarily the fact that
the Claus sulfur plant capacity exceeds requirements because H2S levels
are lower than originally designed for. With the existing sulfur-plant
capacity in four trains, there was sufficient margin to handle
debottlenecked
sour-gas flows plus the flow from a fifth crude oil production train.
The resultant Train 5 project includes a
production train,
new utilities, a plant-wide control room, and a gas-processing plant
that
can handle excess gas from KTL 1 and 2 in addition to Train 5. With the
commitment of these expansion projects, TCO will have a facility by
mid-2000
capable of processing 12 million tpy of crude oil. It was also
recognized,
however, that certain critical off-sites and utilities could not
support
this. In addition, that the infrastructure and long-term environmental
performance required detailed assessment.
TCO was aware of the issues of constraint but
needed to
frame them into a project. This project is called Program 12.
CPDEP execution
Click to enlarge
As do other international exploration and
production companies,
TCO utilizes a structured approach to project planning and execution,
known
as Chevron Project Development and Execution Process (CPDEP), that has
five phases (Table 1).
Each phase has three steps: work execution,
deliverable
production (either a plan or an asset), and management decision to
proceed
to next phase.
Stakeholder communication is an important part of
successful
project execution. To ensure correct decision-making, the end users
must
approve the project at each hold point. Key stakeholder issues for TCO
are the existing plant, language, logistics, regulatory impact, funding
cycles, and the varying financial climate.
This latter point was particularly critical for
the project
because TCO's ability to fund capital projects depends heavily on crude
oil revenue and hence the oil price. At the end of 1997 when the
project
started, the oil price was $18/bbl; by the end of 1998, this had fallen
to $10/bbl. Yet, by mid-1999, it had recovered to $20/bbl.
Phase 1
In October 1997, TCO held workshops in Tengiz
with the
stakeholders to identify the key opportunities and requirements. This
was
documented, reviewed, and a strategy initiated for the work. Fluor
Daniel
was approached to form an integrated team with TCO personnel for the
project-framing
stage that kicked off in February 1998. In parallel, Parsons Group
International
Ltd., London, initiated work on reviewing the existing four sulfur
plants.
The Phase 1 report, issued in April 1998,
detailed the
scope areas for Phase 2 covering oil export, gas and LPG processing,
sulfur
plants, field facilities, and infrastructure.
For the purposes of this article, only the gas
and LPG
aspects of the project will be discussed. The project had the following
objectives:
Minimize or eliminate routine flaring by the
end of Program
12.
Maximize crude oil export volumes by butane
blending,
as economically justified.
Maximize the net present value (NPV) of LPG.
Provide an alternative disposal outlet for LPG.
Gas-plant configurations
As stated, by the time Train 5 is complete,
Tengiz will
have three gas plants, all with similar capacities. The original KTL
gas
plants are essentially identical.
The original configuration was targeted for
flexible production
of sales gas, an ethane-rich petrochemical feedstock, CIS-grade
propane,
CIS-grade "broad fraction" (BF; a poorly fractionated blend of propane,
butane, and some C5+), and debutanizer bottoms for recovery into the
crude.
(CIS = Commonwealth of Independent States, the loose federation that
succeeded
the FSU)
Since there are no local petrochemical plants,
the de-ethanizer
overhead is routed to sales gas, and the associated turbo expanders
were
never commissioned. The single depropanizer produces CIS propane with a
side draw of BF for partial treating.

The product specifications for the CIS-grade
LPG products
are significantly less stringent than for European products.
Consequently,
the gas-plant facilities that are in place make products that TCO
cannot
sell on the world market. Fig. 3 illustrates the process scheme.

The Train 5 gas plant has a significantly
different configuration
(Fig. 4). The key points are that it has no demethanizer (no ethane
product
required) and has a depropanizer and debutanizer with propane and
butane
treaters to provide conventional propane and butane products.
Phase 2
LPG to
FUEL
Advantages
Disadvantages
| Significantly reduces flaring of sales
gas |
Requirement to operate demethanizer
colder |
| Reduces risk to market LPG |
High CAPEX (new gas-export line) |
| Reduces logistics and safety problems
to lower export
volumes |
Cost/viability of converting existing
gas turbines to
burn BF |
|
Poor NPV |
|
Uncertainty over mercaptan distribution
within fractionation
and therefore of being able to meet the sales-gas sulfur specification. |
|
Flare excess BF |
During Phase 2, 14 options for gas and LPG
processing
were evaluated. At present, only a very limited market exists for both
products, and in many circumstances TCO is reluctantly forced to flare
these light hydrocarbons.
LPG to MARKET
Advantages
Disadvantages
| Flaring minimized |
Uncertain sales-gas line condition |
| Broad market for products |
Store, load and export large quantities
of LPG |
| Good NPV |
Transportation logistics of LPG |
| Conventional process operations |
Uncertainty of LPG market |
| Utilize available fractionation
equipment |
Relatively high CAPEX |
| Improves C5+ stream to crude |
|
Five key strategic options were reviewed in
detail:
LPG to LIQUIDS
Advantages
Disadvantages
| Retains focus on core business (oil
export) |
Combined InAlk technology not
operational |
| Increases crude production by 2,500
ton/day |
High CAPEX |
| Postive NPV |
Technologies new to TCO |
| No flaring |
Higher complexity of operation |
| Value for product gasoline potentially
higher |
Capacity requires two InAlk plants |
| No risk of exporting large quantities
of LPG |
Relatively high OPEX |
| Marketing effort limited to crude |
Additional utility requirements |
| Diversity of export outlets |
No alternative routes for LPG during
InAlk |
| Individual InAlk technologies proven |
|
LPG to fuel
The strategy here is to maximize the use of CIS
LPG as
fuel in Tengiz and inject propane into the sales gas up to the
specification
limit. Train 5 propane-butane would be exported. Table 2 shows the
advantages
and disadvantages of this option. LPG to market. This option
(summarized
in Table 3) recovers the propane and butane as conventional products by
revamping the KTL gas plants and LPG storage and export facilities and
using sales gas as fuel in Tengiz.
Typically, LPG volumes on this scale (131
tonne/hr) would
be moved by pipeline, ship, or barge. Since Tengiz is land locked and
constrained
to LPG export by rail, logistics are a key consideration.
LPG to INJECTION
Advantages
Disadvantages
| No safety issues for LPG export |
Condition and capability of injection
wells unknown |
| LPG resource may be recoverable later |
Negative NPV |
| No flaring at Tengiz |
High OPEX, remote manning requiired |
| Simple process technology |
Significant CAPEX |
| Utilises existing fractionation
equipment |
Increased flaring at nearby reservoir
due to higher GOR |
| Reduced rail traffic |
Large number of injection wells |
|
Injection of saleable Train 5 propane |
|
Cost of gaining access to nearby
third-party reservoir |
LPG to liquids
This option (Table 4) converts all LPG to liquid
products,
which can be blended into crude oil or sold as gasoline blend stock.
Sales
gas is used as fuel in Tengiz.
Three suitable LPG-conversion technologies
were identified.
1.1. Cyclar (BP-UOP) converts LPG into
benzene, toluene,
and xylene that may be blended with the crude stream or exported as
aromatics.
2.2. InAlk (UOP) dehydrogenates the C3 and C4
material
and polymerizes these olefins to C6 to C8 material that may be blended
with the crude or exported as gasoline blend stock.
3.3. Fischer-Tropsch (SASOL-type process)
converts the
LPG (and natural gas) to paraffin for export with the crude.
Click to enlarge
LPG PRODUCTS FOR BUSINESS STRATEGIES
| Case |
CIS PROPANE TPH |
CIS BROAD FRACTION TPH |
EURO PROPANE
TPH |
EURO BUTANE
TPH |
SALES GAS TPH |
LPG TO CRUDE
TPH |
FLARE
TPH |
| Base case |
*30 |
*31 |
+26 |
+18 |
398 |
0 |
138 |
| LPG to Fuel |
0 |
*52 |
26 |
18 |
480 |
0 |
11 |
| LPG to Market |
0 |
0 |
75 |
56 |
392 |
0 |
10 |
| LPG to Liquids |
+49 |
+38 |
+26 |
+18 |
392 |
0 |
31 |
| LPG to incineration |
+49 |
+38 |
+26 |
+18 |
398 |
0 |
31 |
| *Product difficult |
to market. |
+Product
|
disposed of |
|
|
|
|
For the unique Tengiz situation, the InAlk
technology
provided the best fit for LPG conversion.
LPG to injection
This option (Table 5) uses Train 5 butane as fuel
in
Train 5 and reinjects all other LPG into a nearby oil reservoir.
Injection
into the Tengiz reservoir was rejected because of the very high
pressure
required and lack of proven pumping technology.
LPG incineration
This option again uses Train 5 butane as fuel,
and then
burns all excess LPG in purpose-built ground flares (Table 6).
Moving ahead
With strategy options reviewed, including
technical and
financial cases for each, a recommendation was needed for management
and
partner approval. Table 7 summarizes LPG production and disposition for
each case including a base case, or "do nothing" case.
Financial modeling was developed to determine the
NPV
of each case. This was then fed into a decision risk analysis,
including
a series of sensitivity analyses.
LPG to market was recommended and approved.
The option
was chosen because it:
Provides a significant NPV for the LPG product
Minimizes flaring
Provides opportunity to slip some butane into the
crude
up to the vapor pressure limit if economically justified
Can be implemented in stages to provide
significant flare
reduction in the short term, realize LPG revenue, satisfy budget and
cash
flow constraints, and prove up the market prior to full investment.
Phase 2 of this project lasted from May until
November
1998.
Phase 3
As mentioned, a feature of the LPG-to-market
strategy
is the ability to stage the work to meet TCO's cash flow objectives yet
achieves early increases in LPG export.
The implementation plan is phased over three
stages.
The Stage 1 scope is to:
Install a propane treater and drier in KTL-1,
which will
also treat propane from KTL-2 (note lower flow rates prior to
fractionation
modifications).
Upgrade the LPG storage and rail loading
facilities.
Install a sweet-gas crossover system from KTL-1
and KTL-2
to load the Train 5 gas plant.
This stage gives a fast track to facilitate
export of
Train 5 LPG products, maximize Train 5 gas plant utilization, and
export
a substantial quantity of the existing KTL propane. It leads to a
significant
reduction in flaring coincident with Train 5 start-up.
Stages 2 and 3 install full LPG fractionation,
complete
LPG treating, and install sour-gas cooling and condensate-stripper
reboiler
upgrades, first in KTL-1 and then KTL-2.
Program 12 has a CAPEX budget exceeding $300
million,
more than half of which is for the LPG upgrade.

Fig. 5 summarizes the status of the process-unit
capacities
after Program 12.
Due to the level of study and definition
performed in
Phase 3 and the fast-track nature of the Stage 1 work for the propane
treater,
stakeholder approval was managed so that approval of the strategy and
funding
for Stage 1 was achieved by December 1998. This was critical so that
the
treater package could be delivered to site (which for skids of this
size
is only viable by ship or barge) before the weather window closed in
autumn
1999.
If transportation were delayed until the
Volga-Don canal
opened in spring 2000, start-up to coincide with Train 5 would be in
jeopardy.
Phase 3 culminated with approval for funding
of this full
scope in June 1999. The aggressive schedule for the Stage 1 treater was
achieved with the placing of the modules on the foundations in December
1999. In addition to front-end engineering and design, Phase 3 included
many studies to address issues raised during Phase 2, which did not
affect
the overall strategy.
Following is a discussion on three significant
technical
issues.
LPG treater
With the move to market LPG to Western
specifications,
the LPG treating for sulfur removal had to be addressed. The
comparative
sulfur specifications for the CIS and Western products are: CIS
propane,
H2S and mercaptan sulfur-130 ppm (wt);
CIS BF, H2S and mercaptan sulfur-250 ppm (wt),
H2S-30
ppm (wt); in contrast, Western propane and butane: H2S-0.5 ppm (vol),
H2S
+ COS-1 ppm (wt), total sulfur-15 ppm (wt).
The Tengiz reservoir with its high H2S content
is also
characterized by a high level of organic sulfur species: heavy
mercaptans,
light mercaptans (RSH), and COS.
This presents two significant challenges:
predicting the
distribution within the process plant and their removal by different
processes.
The heavy mercaptans predominantly stay with the crude oil and are not
such a safety or environmental concern as the light (predominantly
methyl
and ethyl) mercaptans. Prediction of the disposition of the light
mercaptans
and COS within the process train due to physical processes (cooling,
flashing,
distillation) and absorption processes (amine DEA) is difficult. TCO
has
undertaken extensive field laboratory analysis and correlation against
process simulation and thermodynamic packages.
Similarly, the removal efficiencies using DEA
in the main
amine sweetening process have been reviewed. The results of this work
have
been fed back into the simulation models to provide the best pragmatic
fit. The light mercaptans and COS demonstrate limited absorption in the
gas sweetening amine unit, and work their way through predominantly
into
the LPG products. The light mercaptans must also be limited in the
sales
gas; this and the Wobbe number specification dictated the demethanizer
and de-ethanizer operating conditions. This drives the sulfur species
into
the LPG. Therefore, a robust solution for LPG sweetening is required.
Light mercaptans will be present in both
propane and butane
but can be removed readily using Merox-type technology with a
sponge-oil
system to remove disulfide oil. Removal of small quantities of H2S in a
caustic-based treater is not an issue. But the COS is known to migrate
into the propane stream.
Removal of the COS is the most significant
technical
challenge. COS can be removed with selected amines by staged contacting
devices. Tengiz treater designs are constrained by the desire to use
the
site amine, DEA. Not the optimum amine for this application, DEA is
nevertheless
the typical amine used in refinery applications. DEA is used at site
currently
for removal of COS from BF in a mixer and settler system. The
efficiency
of the stages, however, is relatively poor, and the specification of 1
ppm H2S + COS is far from achievable.
Consequently, a key consideration is the stage
efficiency
of the contactor device. Several existing LPG treaters operate at site
with varying success.
The Train 5 project, proceeding ahead of
Program 12, had
already placed orders for COS and mercaptan treaters from Merichem
Chemicals
and Refinery Services, Houston. This scope consisted of:
Propane: Two-stage DEA Aminex and single-stage
caustic
treater
Butane: Two-stage caustic treater and a common
caustic
regeneration unit
Program 12 has a clear requirement for LPG
treating, but
evaluation was required to formulate a strategy and confirm that the
COS-removal
technology works. The following options were considered: install,
modify,
or revamp existing equipment; procure and install Train 5 copies.
Given the status of existing equipment, it was
clear that
additional LPG-treating capacity would be required in any case. In
recognition
of the staged execution strategy, a propane COS/RSH treater was needed
on a fast-track basis.
For several reasons, including equipment
commonality,
a repeat order was placed with Merichem for a Train 5-type propane
treater
and caustic regeneration unit to be installed in KTL-1. A propane drier
repeat order was also placed. The technical risk of achieving the COS
specifications
was reviewed in detail by Merichem, Chevron specialists, and Fluor
Daniel
technical experts. The Merichem Aminex process uses a two-stage
countercurrent
design with co-current Fiber Film technology to provide the contact
area
and residence time.
Although there were no reference units for this
technology
in operation using DEA, Merichem has worked closely with Chevron,
initially
at a refinery and subsequently in laboratory trials. The key to
performance
is the ability of DEA to absorb COS and the stage efficiency of the
Fiber
Film contactor. Merichem expects the exit COS to be 0.5 ppm and
guarantees
1 ppm. The feed temperature of 54° C. is critical. After close review,
we were able technically to support the expected performance and remove
this as an issue.
The clear commercial and technical solution was
to remove
the existing treaters and install duplicate Train 5 units in both KTL-1
and 2.
LPG storage, loading
Tengiz has an existing LPG storage and
rail-loading facility.
For the LPG-to-market strategy, this facility is key. The Tengiz LPG
export operation will be world scale, considering
the
volumes to be loaded and rail car movements.

The existing facilities consist of a remote
bullet park
with 40 bullets and 4 pumps of varying capacities. The rail-loading
rack
is all manual with 60 railcar loading slots representing the capacity
of
a single train. Although the storage and loading capacity is adequate
for
limited export, the existing facilities are not configured
appropriately
and do not satisfy the safety and operational requirements of TCO,
especially
considering the substantial increase in throughput.
In parallel with review of revamp options, new
facilities
based on spheres and semi-automated railcar loading systems were
reviewed.
The existing facilities were surveyed by an external peer group of
LPG-handling
specialists, and a strategy for an economically viable revamp was put
forward.
This supported the desire to continue to
utilize the existing
bullets and rail-loading rack, which are fit for purpose. Various
upgrade
strategies were reviewed with a fit-for-purpose discrete event analysis
tool.
Critical parameters for review included setting a
strategy
for sampling and laboratory analysis of the product before generation
of
an export passport and determining the optimum loading rates and
loading
system flexibility against storage volume and manpower requirements to
support varying marketing requirements.
The stakeholders reviewed the strategies and
approved
the selected strategy: 20 revamped bullets, with a further 10
identified
for future revamp, and all 60 loading slots available.
As has been recognized earlier, the logistics of
the
operation reliably to load and transport of 96 rail tank cars (RTCs) a
day is a major challenge. TCO will have upwards of 5,000 RTCs on
long-term
hire to support this operation. Peripheral operations such as RTC
movement
tracking, cleaning, and maintenance also become a major factor.
The scope of the revamp is summarized as
follows:
Three additional rail car sidings
Fire protection upgrade including detection, fire
fighting.
and firewater impoundment
Replacement of some stairs and platforms
Reconfigure relief valve headers
Cleaning and upgrade of 20 bullets, 13 propane, 7
butane
Remove fuel-gas blanketing to prevent product
contamination
and provide nitrogen for purging
Off-spec rerun system to plant
Pairing of bullets, bullet-level instrumentation,
and
ESD /switching isolation
*New loading-pump suction headers, ESD valves
and canned
loading pumps, 350 cu m/hr propane, 175 cu m/hr butane.
Storage park and plant data link, ESD and control
systems.
Conversion of loading spots to incorporate new
valving,
10 propane, 30 propane+ blend , 20 butane+ blend.
LPG blender and composite samplers for all three
products.
Data capture
A critical need of design engineers when working
on brownfield
projects has been to have ready access to accurate data for the
existing
plant. Without this, retrofits and plant modifications cannot be
efficiently
executed.
Although this need has remained constant over
the years,
what has varied is the capability of technology and industry to acquire
the data. This capability has grown from simple use by field-based
designers
of rulers and sketchpads to the application of more advanced
technologies
such as photogrammetry and laser scanning that enables plant data to be
captured without the need physically to measure.
Fluor Daniel has significant experience in
application
of both techniques, and the project evaluated available survey methods
in order to select the most fit-for-purpose solution. Key factors in
this
evaluation included:
Lack of existing drawings
High cost of placing designers in the field
Requirement to minimize physical contact with
live plant
due to safety considerations
Schedule drivers requiring fast acquisition of
data
Physical size of plant areas, for example,
requiring
more than 7,000 photographs for photogrammetry
Extreme environmental conditions for surveying
(temperatures
typically in the high 40s° C., sandstorms, and large daily diurnal
changes
being recorded)
Inaccessibility of some areas of process plant
would
have resulted in inaccuracy if physically measured
Laser scanning techniques have evolved so that
they are
economically viable for data capture on process plants. The project has
evaluated UK Robotics, which has developed a laser scanning system that
captures more than 11 million data points in a 2-min scan, thus
overcoming
many of the time and cost issues associated with plant data capture.
This data-capture mechanism is supported by
software that
enables the user to view the data in either 3D "photobrowser" (giving
the
ability to take desktop measurements from the scanned images with an
accuracy
of 6 mm) or an engineering 3D CAD model. Thus, the information can be
represented
in the format is most appropriate to the project.
Given the challenges of the location, it was
crucial
to be able to view and analyze the collected data at site immediately
after
collection. The modeling software enabled this to be carried out on
completion
of each 2-min scan and highlighted any deficiencies.
It would clearly be unacceptable to realize a
problem
existed with the captured data after the surveyors had returned to the
UK.
The project would have taken a significant amount
of
time and been very labor-intensive if either manual data capture or
photogrammetry
had been used. With laser scanning and close liaison with the client's
team in Tengiz, the data was captured within 5 weeks.
A total of 80 gb of data were recorded, which
clearly
offered significant time and cost benefits to the project. In addition,
the data captured were downloaded to CD and viewed back in the UK
offices
much more quickly than would have been possible with technology that is
more standard. This was extremely important to the project because
early
engineering decisions could be taken from measurements made using the
3D
photobrowser.
The Authors
Dave Connell is the engineering and procurement
manager
on Program 12. Previously, he was engineering manager on the Train 5
expansion
project for the Tengiz field. He has worked for Chevron since 1977 in
various
engineering and project assignments. He holds a BS in chemical
engineering
from the University of Arizona.
Connell served as chairman of the European
Chapter of
the GPA in 1998 and has been a member of the management committee for
the
past 7 years.
Bob Ormiston retired in March 2000 after 33
years with
Chevron. For the majority of that time, he held various
process-engineering
positions and most recently was in project management. He was one of
the
earliest Chevron employees to be assigned to Tengiz, leading the
on-site
process engineering team and finally as project engineer on Program 12.
Ormiston holds a BSc in applied chemistry from Glasgow University and a
PhD in chemical engineering from Cambridge University.
Nick Amott is a senior manager, process
engineering with
Fluor Daniel in the UK. He has been with the company for 19 years,
holding
various process-engineering positions. Previously, he worked for Lummus
for 4 years. Amott holds a BSc (1978) in chemical engineering from the
University of Surrey and is a Fellow of the Institution of Chemical
Engineers.
Irene Cullum, lead process engineer for
Program 12, worked
with Fluor Daniel since 1990. Previously, she worked for Kaldair and
Sasol.
Cullum holds a BSc (1980) in chemical engineering from the University
of
the Witwatersrand, South Africa, and a MASc in chemical engineering
from
the University of Toronto.
Based on a presentation to 79th Annual GPA
Convention,
Mar. 13-15, 2000, Atlanta
|