Back to Country Information

SAKHALIN OIL AND GAS PROJECTS Sakhalin II Offshore Pipe Laying Completed Ahead Schedule
Sakhalin-V energy project exploration set to continue 2006
Sakhalin 2005 Energy Information Agency

Sakhalin II Offshore Pipe Laying Completed Ahead Schedule
Sakhalin Energy 8/30/2006

In a season of milestone achievements, Sakhalin Energy has reached another significant milestone by completing the laying of its Piltun area offshore pipelines ahead of schedule, thus concluding all offshore pipelaying work for the Sakhalin II Phase 2 Project.

Sakhalin II Deputy CEO and Phase 2 Project Director David J. Greer underlined the importance of this achievement: not just for the Project, but also because it was achieved without impact to the Piltun environment, the area most sensitive to the Western Gray Whales (WGW).

An extensive noise monitoring campaign throughout the 2006 offshore season, also monitored in parallel by NGOs, showed that construction never exceeded the established noise criteria. With the work now finished ahead of schedule, the Company has been able to start demobilizing vessels in advance of original plans, effectively minimizing the overall acoustic footprint.

"All of Sakhalin Energy's efforts over the last few years, including our extensive investment, research and ongoing work with the independent WGW experts, bring us to where we are today – announcing that we have safely and successfully finished our offshore pipelaying work without having compromised the safety of the endangered Western Gray Whale", said David Greer. "This is something that the Company is extremely proud of."

Sakhalin II's offshore pipeline – consisting of extra-heavy pipe with thick concrete coating to ensure stability under all conditions – in water depth shallower than 30 meters has been buried in a deep trench to protect against ice scouring.

This year's offshore pipeline works followed on from the work Sakhalin Energy completed in summer 2005 in the Lunskoye area. The 2006 summer work has included dredging, installation and backfilling works on four separate pipelines: an oil and a gas pipeline from Chaiyvo beach to the new Piltun-B platform; and an oil and a gas line from Chaiyvo beach to the existing Piltun-A platform (Molikpaq). Total combined length of these pipelines exceeds 230 kilometers.

With pipelaying now complete, the only outstanding offshore pipeline work involves divers making the final connections between the pipelines and the platforms. This is planned to be done before the end of the 2006 offshore construction season and will be followed by hydrotesting of the pipelines.

The offshore pipeline work forms an important element of the Sakhalin II Phase 2 Project. Among other elements are Russia's first LNG plant, oil export terminal, onshore pipelines, two new offshore platforms and onshore processing facility. Overall design, procurement and construction work on the Phase 2 project is currently over 75% complete.


Sakhalin II Offshore Pipe Laying Completed Ahead Schedule
Sakhalin Energy 8/30/2006

In a season of milestone achievements, Sakhalin Energy has reached another significant milestone by completing the laying of its Piltun area offshore pipelines ahead of schedule, thus concluding all offshore pipelaying work for the Sakhalin II Phase 2 Project.

Sakhalin II Deputy CEO and Phase 2 Project Director David J. Greer underlined the importance of this achievement: not just for the Project, but also because it was achieved without impact to the Piltun environment, the area most sensitive to the Western Gray Whales (WGW).

An extensive noise monitoring campaign throughout the 2006 offshore season, also monitored in parallel by NGOs, showed that construction never exceeded the established noise criteria. With the work now finished ahead of schedule, the Company has been able to start demobilizing vessels in advance of original plans, effectively minimizing the overall acoustic footprint.

"All of Sakhalin Energy's efforts over the last few years, including our extensive investment, research and ongoing work with the independent WGW experts, bring us to where we are today – announcing that we have safely and successfully finished our offshore pipelaying work without having compromised the safety of the endangered Western Gray Whale", said David Greer. "This is something that the Company is extremely proud of."

Sakhalin II's offshore pipeline – consisting of extra-heavy pipe with thick concrete coating to ensure stability under all conditions – in water depth shallower than 30 meters has been buried in a deep trench to protect against ice scouring.

This year's offshore pipeline works followed on from the work Sakhalin Energy completed in summer 2005 in the Lunskoye area. The 2006 summer work has included dredging, installation and backfilling works on four separate pipelines: an oil and a gas pipeline from Chaiyvo beach to the new Piltun-B platform; and an oil and a gas line from Chaiyvo beach to the existing Piltun-A platform (Molikpaq). Total combined length of these pipelines exceeds 230 kilometers.

With pipelaying now complete, the only outstanding offshore pipeline work involves divers making the final connections between the pipelines and the platforms. This is planned to be done before the end of the 2006 offshore construction season and will be followed by hydrotesting of the pipelines.

The offshore pipeline work forms an important element of the Sakhalin II Phase 2 Project. Among other elements are Russia's first LNG plant, oil export terminal, onshore pipelines, two new offshore platforms and onshore processing facility. Overall design, procurement and construction work on the Phase 2 project is currently over 75% complete.

Sakhalin-V energy project exploration set to continue
Source: RIA Novosti 09-06-06

Shelf exploration as part of an ambitious energy project in Russia's Far East has resumed after a crucial port reopened to summer shipping, a logistics company said.
A spokesman for Sakhalin Shelf Services said the northern Sakhalin port of Moskalvo, which is only accessible from early June to early November, would take equipment supplied by Elvari Neftegaz to explore deposits as part of Sakhalin-V.

Elvari Neftegaz, set up by project operators Rosneft, Russia's state-owned oil company, and British major BP, will drill at the Kaigansky-Vasyukansky deposit.
Sakhalin-V covers the Kaigansky-Vasyukansky deposit, whose recoverable oil reserves are estimated by Rosneft at 1.171 bn tons (8.6 bn barrels), and Vostochno-Shmidtovsky deposit with estimated recoverable reserves of 411 mm tons (3 bn barrels) of oil and 255 bn cm of gas.

Production was launched late last year at 2,200 barrels of oil per day.
Analysts have said the project will be cost-effective due to short oil-delivery routes to the energy-hungry Asia-Pacific region.
Sakhalin island looks to boost its visibility
By PATRICK GILL / The Russia Journal
Far East representatives hope Moscow exhibition will attract investment.

Representatives of the Far East Russian island of Sakhalin hope an exhibition this week in Moscow will boost the region’s visibility and help attract business and investment. At "Sakhalin in the 21st Century," March 28-30 at the Federation Council in Moscow, business and government leaders will discuss economic developments, legal changes and improving Sakhalin’s relations with other regions. Representatives from oil, coal mining, science, transport, fishing, light industry and financial structuring companies – 22 in all – some making the long trip from Sakhalin to Moscow, will promote their goods and services.

"Sakhalin is second only to Moscow for foreign investment in Russia and is number one in the Far East," said Michael Allen of the American Business Center in Yuzhno-Sakhalinsk, the island’s main city.  "It saw a jump from $140 million in 1998 to $1 billion last year. In 2000, we expect this figure to drop to around $500 million – a hiccup that is largely due to ExxonMobil’s drilling program having been held up by difficulties in obtaining a license." Allen said that the "main oil and gas projects are currently Sakhalin 1 and Sakhalin 2, product-sharing agreements started in 1996 that began extracting oil from the Sakhalin shelf last year. In addition, there are two or three more product-sharing agreements waiting in the wings."

Offshore July 2003 wwwoffshore-mag.com
Sakhalin II will without a doubt be the largest of its kind for some time to come.  Now that the final investment decision on this $10 billion project has been made, Shell is already working hard with the Russians to optimize participation.  'Me project will be operated by Sakhalin Energy

The giant Sakhalin Phase II project will test the skills of shell’s EP Projects team.

Investment Co., of which Shell holds 55% along with partners Mitsui, 25%, and Mitsubishi, 20%. This massive project includes oil and gas development as well as an LNG facility.  One of the project requirements is that it includes 70% Russian content. A Russian group has been established to devise a candidate list of contractors with the necessary qualifications and background to work on the project.  In addition to the in-house capabilities of such companies, joint ventures will be considered with international companies.  This will ensure that the best available technology is used on the project and will facilitate a transfer of technology to Russian firms for future application.

According to Greer, there is already a considerable amount of civil engineering expertise available in Russia, and this makes a good starting point for the skills needed on Sakhalin.  This project will have a life of 30-40 years, so it is critical to promote the development of skills required for this project within the domestic Russian labor force. While Sakhalin 11 will be a major undertaking, Greer said, none of the technology itself is new to Shell.

Part of how the EP Projects group evaluates its role in such undertakings is to consider what the local operating unit of Shell has to offer.  The global EP Projects staff then enhances these capabilities.  Shell has broad experience in LNG projects for example.  The company also has extensive surface and subsurface expertise.  Still, the operating unit will certainly need additional manpower and may require technology that it is not familiar with.  These are areas where EP Projects will help.

Another example of how EP Projects interacts with the rest of Shell is the group's involvement on the Bonga FPSO offshore Nigeria.  This FPSO was a huge technical step change for Shell's Nigeria operation.  Greer said the company had to assess its capabilities in that country.  The decision was made that the technical expertise was held by Shell in Houston.  So it was necessary to transfer this knowledge to the Nigerians who would be operating the facility.

While the industry continues to lament the small number of new engineers who choose a career in E&P programs like EP Projects ensure that the new recruits who do come in will have the support they need to succeed and a variety of fascinating challenges to help them develop.  EP Projects' future is filled with opportunities.  

This year, foreign investors are expected to inject $350 million into the oil-shelf projects off Sakhalin, with each dollar of direct investment in shelf projects yielding two dollars for the local economy, officials said. Sakhalin is the fourth largest in industrial manufacturing out of the nine Far East regions, a figure the exhibition hopes to improve this year. The local mining industry has already undergone improvements – 20 worked-out mines have recently been replaced, a step which local authorities hope will lead to cheaper coal supplies and lower overheads for industry.

One problem facing the local economy is the dwindling deposits of onshore oil and gas fields. These are substantially depleted, and oil extraction has been declining continuously since 1984.  The good news for the area is that new fields have recently been discovered off the northeast shore of the island. The island has substantial resources of oil, gas, coal and gold, with oil and gas the main areas of foreign investment – constituting 15 percent of Sakhalin’s total commodity output.

The island, with a population of 670,000, is seven hours ahead of Moscow time and situated in the Okhotsk Sea north of Japan. Russia and Japan have been in conflict since the early 19th century over the volcanic Kuril islands, which neighbor Sakhalin. Russia won back the islands along with southern Sakhalin after World War II, although the dispute continues as Japan still lays claim to the islands. Earthquakes continuously threaten Sakhalin and the Kurils, the most destructive in recent times being the 1995 quake, which destroyed the Sakhalin town of Neftegorsk.

Next month, a new, major project involving supplying electricity from Sakhalin to Hokkaido, Japan, is set for approval. The $12 billion plan was first discussed between Anatoly Chubais and the governor of Sakhalin two years ago, and should become a reality after feasibility studies are completed in April, officials said.

(Information on the exhibition can be obtained by calling the Sakhalin representative in Moscow at 203-5141.) 

BISNIS Russian Far East/Oil and Gas Update, 21 July 2003
KHABAROVSK KRAI COMPANIES & SAKHALIN OIL AND GAS PROJECTS

AUTHOR: ANDREI VASENYOV, BISNIS REPRESENTATIVE IN KHABAROVSK, RFE

SUMMARY
The Sakhalin oil and gas projects, which have grown into one of the largest direct investments in the Russian economy, involve the participation of a large number of Russian and foreign suppliers, manufacturers, construction and design companies and accompanying service providers. The operators of the Sakhalin projects seek to increase the Russian content by contracting with as many Russian companies as possible. Several Khabarovsk Krai (territory) companies have successfully won tenders and obtained contracts to work on the Sakhalin projects. However, many other Khabarovsk companies fall short of becoming contractors, subcontractors, and suppliers because they fail to meet high safety, environmental, standardization and other requirements set by the project operators. Finding a suitable U.S. partner could substantially increase the chances of Khabarovsk Krai companies winning contracts for supply of machinery, parts, or services and, at the same time, could help an American company to enter this market. 

SAKHALIN PROJECTS OVERVIEW
The Sakhalin oil and gas projects were the first in Russia to employ production-sharing agreements (PSAs). This approach attracted a huge amount of foreign investment by providing favorable tax procedures (substitution of the majority of federal and local taxes with product sharing) and guaranties of stability for the whole period of the project implementation activities (30-40 years). This, in turn, allowed for the successful development of these large-scale projects in harsh environmental and climatic conditions.   Sakhalin-1 Sakhalin-1 is the second project implemented under a PSA on the Sakhalin shelf. The estimated recoverable reserves of Chaivo, Arkutun-Dagi, and Odoptu deposits total 307 million tons of oil and 485 billion cub. m. of gas. The expected daily oil production amounts to 250,000 barrels (33,000 tons per day). Sakhalin-1 project intends to develop these oil and gas resources in phases, using both offshore and onshore wells. The first phase of development will focus on the Chayvo and Odoptu fields, with first oil expected from Chayvo at the end of 2005 and from Odoptu in early 2007. The oil will be exported via pipeline to a marine tanker terminal at DeKastri (in Khabarovsk Krai). Limited gas production will be available in this initial phase to help meet Russian domestic demand. Future phases of development envision construction of a natural gas pipeline to Japan and development of the Arkutun-Dagi field. 

The consortium developing Sakhalin-1 comprises U.S., Russian, Indian and Japanese companies, which will invest as much as $12 billion throughout the life of the project. The members of the consortium are Exxon Neftegas Limited, USA (30 percent shareholder), ONGC Videsh Limited, India (20 percent); RN-Astra, Russia (8.5 percent); Sakhalinmorneftegas-Shelf, Russia (11.5 percent); and Sakhalin Oil and Gas Development Co., Ltd., Japan (30 percent). Exxon Neftegas Limited, a subsidiary of U.S.-based Exxon Mobil Corporation, is the operator of the project.

According to Neil Daffin, the President of Exxon Mobil Limited, once the Sakhalin-1 project has proceeded to the exploitation stage, the projects’ costs increased considerably. Russian companies are winning an increasing number of tenders. In 2002, many Russian businesses obtained large contracts, and the overall value of contracts signed with Russian suppliers and contractors exceeded $1 billion.

Sakhalin-2
Sakhalin-2 was the first Russian project to be implemented under the PSA regime. The total calculated recoverable reserves of the two offshore deposits, Piltun-Astohoonskoye (oil deposit) and Lunskoye (gas deposit), are estimated at 150 million tons of oil and 642 billion cub. m. of natural gas. The operator of Sakhalin-2 project is the Sakhalin Energy Investment Company Ltd. (SEIC), composed of Mitsui (Japan) - 25 percent share, Mitsubishi (Japan) - 20 percent, and Royal Dutch/Shell (UK/Netherlands) - 55 percent. During 1996–2001, approximately $2 billion was allocated for the project implementation. The direct profit of the Russian side, including bonuses, payments to the Fund for Sakhalin Development, reimbursement of the preliminary Russian expenditures for the exploration activities was $181 million; Sakhalin Oblast received $154 million.

The Sakhain-2 project is responsible for the development of the local industrial infrastructure needed oil and gas production. The approved Complex Plan for the project development envisions total capital investment exceeding $8 billion. Once the production facilities reach their pre-planned production capacities, the annual extraction of oil and condensate within the Sakhalin-2 project will amount to 8.5 million tons; natural gas - 19 billion cub. m.

Sakhalin-3 Sakhalin-3 project encompasses the development of two independent projects: Kirinskiy Perspective Block  (roughly 687 million tons of oil and condensate, 873 billion cub. m. of natural gas) and Vostochno-Odoptinskiy & Ayashskiy Perspective block (roughly 160 million tons of oil and condensate, 67 billion cub. m. of natural gas). Both projects require geological and exploration research to determine the exact volume of recoverable oil reserves and exact location of oil and gas deposits. The operator and investor of the first project is PegaStar (USA); its founders are Mobil Russia Ventures Inc, Texaco Exploration Sakhalin Inc, NK Rosneft and Rosneft-Sakhalinmorneftegas JSC. The investors of the second project are Exxon Neftegas Ltd, NK Rosneft and Rosneft-Sakhalinmorneftegas JSC.

PARTICIPATION OF KHABAROVSK KRAI COMPANIES IN SAKHALIN PROJECTS
While striving to maximize Russian content and contract as many local companies as possible, the operators of Sakhalin-1 and 2 keep in mind a number of requirements when evaluating candidates and selecting eligible contractors and suppliers. Safe operation, compliance with environmental regulations and existing legislation, competitiveness of costs and the ability to deliver the requirements on schedule are among the primary demands.   The Sakhalin-1 project operator Exxon Neftegas Limited has been successfully working with the Sakhalin Oblast Administration and the Russian Ministry of Economic Development and Trade to establish a Joint Committee on Russian Content. In order to inform Russian suppliers and subcontractors about the project objectives, standards, and bidding procedures and to increase their competitiveness, special Russian supplier seminars were held in Khabarovsk, Yuzhno-Sakhalinsk, and Moscow. Russian and English-language websites (www.sakhalin1.com and www.sakhalin1.ru) were launched to inform potential contractors and vendors about major contracting opportunities and upcoming tenders.

Activation of the Sakhalin oil and gas projects during the last 3 years resulted in an increase of the Khabarovsk Krai companies’ participation. As of early 2003, six major contracts were signed with the Khabarovsk Krai companies worth some $200 million. Current Sakhalin contractors are Amurskiy Shipbuilding Yard (Komsomolsk-on-Amur), Vostok airline (Khabarovsk), and Dalmostostroy (Khabarovsk). Three Khabarovsk Krai design institutes-- DalTISIz, Dalaeroproekt, and Dalgidrovodokhoz--have also been extensively involved in the projects. 

Transportation Companies  On June 2003, Exxon Neftegas Limited signed its second 5-year contract with Vostok airlines JSC from the Khabarovsk Krai. The company was established in 1945 and in 1993. Fifty-one percent of the airline’s shares belong to the federal government, 22.75 to the Krai government, and 26.25 percent to private shareholders. Vostok’s primary fleet consists of seven Mi-8MTV helicopters, Mi-8T, six An-28 planes, and three An-38-100 planes. Since 2001, Vostok is an official provider of airline services for the United Nations in East Timor.

Vostok obtained its first Sakhalin contract for the provision of air transportation services in 1997, surpassing four competitors. Although this was the airline’s first exposure to the contractors’ selection system, it was able to comply with tough requirements of the project operator, which included the availability of the fully prepared aircraft, flight safety management systems, and qualified aircrew and technical personnel. Especially strong attention was paid to personnel discipline. In order to be eligible for participation in the Sakhalin-1 project, Vostok airline had to obtain some specialized certificates. 

Construction Companies In autumn 2002, Exxon Neftegas Limited contracted with Dalmostostroy JSC (Far Eastern Bridge Construction Company, Khabarovsk) for the construction of Chaivonskiy Bridge. The 830-meter bridge will connect the drilling site on the Chaivo Island with the coastal product-processing complex. The passage will first be used to transport heavy (600 tons) production equipment, and after production begins will serve for the daily transportation of personnel and cargo to the drilling site.

Construction of the Chaivo bridge is one of several projects recently passed over to Russian subcontractors by ABB Lummus Global (Moscow) as a part of the company’s own contract for the detail planning, logistics support, and construction of coastal facilities for Sakhalin-1 project. The other projects involve SakhNIPImorneft (design) and Sakhalinmorneftemontazh JSC (general construction) Sakhalin companies and Amurskiy Shipbuilding Yard (Komsomolsk-on-Amur, Khabarovsk Krai). The shipyard was contracted for the construction of 54 reservoirs for storage of diesel fuel and hydrocarbon base for drilling liquid.

In 1996, Amurskiy Shipbuilding Yard JSC became a prime contractor of Sakhalin Energy to modernize Moliqpak, an offshore oil-drilling platform. In 2002, the shipyard and Exxon Neftegas Ltd signed a contract on refitting and modernization of Orlan, an oil-drilling platform in the framework of Sakhalin-1 Project. Other parties of the $140 million contract include Hyundai (Republic of Korea) and Natchik (USA). As a result of the shipyard’s new contract to refurbish the Orlan platform, its partner, FIAS (USA) obtained a $ 31 million contract to act as the procurement company - procuring all parts of equipment and dealing with certification, inspection, and logistics.

The shipyard intends to expand its participation in Sakhalin projects and plans to lease working premises at the Severny shipyard (Sovgavan). The shipyard’s primary business activity is production of machinery (propellers, shaft, steering gear, winches, capstans, ladders, bridge bearings, screws, etc.). In general, the yard comprises hull, assembly and welding, pipe assembly, machinery, metallurgical, heat treatment production, a testing center, and electroplating shops. The enterprise produces sea and river vessels, vessels with air pillow maintenance, vessels with hydrofoil wings, ocean trawlers and refrigerators, and others. 

Over 60 Khabarovsk Krai companies have submitted applications for participation in upcoming Sakhalin tenders. Even a larger number of Krai enterprises wish to become suppliers or contractors of the Sakhalin oil and gas projects. The primary reasons why many Khabarovsk Krai companies failed to win tenders are lack of international business experience; failure to produce equipment that meets the environmental, climatic, technical or ergonomic requirements; failure to ensure stable on-time delivery of their products and/or services to the destination site; poor safety records; and a lack of quality and standards certifications.

Many of Khabarovsk Krai enterprises are willing to establish joint ventures with U.S. companies so that they can expand their services and improve the quality of their products to meet higher international quality requirements. At the same time, the U.S. companies could also benefit from such partnership and become subcontractors to their Russian partner or win subsequent tenders to supply equipment, machinery, parts, services, etc.

CONSORTIUM OF THE RFE ENTERPRISES  In order to promote the participation of Khabarovsk Krai companies in Sakhalin oil and gas projects and increase their competitiveness through informational and legal support, the Krai Government and a number of large manufacturers, suppliers, services providers, transportation companies and design institutes seek to establish a consortium of Russian Far East companies. The consortium will obtain the legal entity status once it receives state registration. Its headquarters will be located at Amurskiy Shipbuilding Yard JSC, and the shipyard’s director will be responsible for the organization of the consortium structure and attraction of Khabarovsk manufacturers and suppliers to participate in the construction of the Orlan platform.

The consortium will assist its members in completing tender application documents for the preliminary competition and selection stages and organize and conduct specialized training seminars and courses for the top managers of the companies. It will also provide informational services, including compiling of databases, conduct and participate in symposiums, conferences, exhibitions and other events. The members of the consortium seek to develop partnerships with similar foreign and international organizations to share experience. The consortium’s activities are expected to increase Khabarovsk firms’ chances of obtaining contracts.

CONTACT INFORMATION

U.S. Consulate General Vladivostok U.S. Commercial Service  32 Pushkinskaya St., Vladivostok, Russia Tel: (7-4232) 49-93-81 Fax: (7-4232) 30-00-92 Email: William.Lawton@mail.doc.gov  Contact: William S. Lawton, Principal Commercial Officer    BISNIS in Khabarovsk 18 Muravyeva-Amurskiy Street, office 307 Khabarovsk 680000, Russia Tel/Fax: (7-4212) 305-757 Email: bisnis@vasandr.kht.ru  www.bisnis.doc.gov www.bisnis-eurasia.org Contact: Andrei Vasenyov, BISNIS representative

For contact information of relevant Khabarovsk krai officials and brief descriptions/contact details of Khabarovsk Krai Companies that are acting and potential contractors of Sakhalin oil and gas projects, please contact 

Ellen House, BISNIS trade specialist for the RFE  email: Ellen_house@ita.doc.gov, tel: 202-482-2284 or Chris Christov, BISNIS trade specialist for oil and gas sector email: chris_christov@ita.doc.gov, tel: 202-482-4199

To use MyBISNIS, go to: www.bisnis.doc.gov/MyBISNIS.cfm

June  2003
June 2006